Great Basin Water Company-SCD Pipeline Replacement Project

SERVICE STUDIO: Community Planning, Civil Infrastructure Engineering, 1704 Special Inspection, and Material Testing & Inspection
Location: Elko, Nevada
Project Manager: Thomas Hannum, P.E./Nitin Bhakta, P.E.

Brief

Summit Engineering performed all the surveys needed for phases 1 thru 5 for the Great Basin Water project in Spring Creek, Nevada. Our surveyors performed site surveys to include existing locations on the water main, and fire hydrants as well as existing water meter locations, existing fence, existing above-ground, and underground utilities such as fiber optic, gas, electrical, and telephone locations. In addition, ground elevation to tie existing storm drains and roadside drainage channels. Performed construction survey for the project to stake location of new water main, new hydrants, and location for jack & bores under the roadway. We also provided an as-built survey for Great Basin Water to verify quantities and pay requests.

Scope

Summit Engineering performed inspection and testing services for the Great Basin Water Project in Spring Creek, Nevada. Duties performed were compaction testing, concrete testing, verification of thrust blocks on all new hydrant’s placement as well as hydrostatic pressure testing on new water mains. In addition, Summit also verifies all jack and bore trenching and casing placement. Verified lineal footage of waterline placement as well as testing of water in new mains for bacteria. We also submitted as-built plans and reports to NDEP for new final review and acceptance.

Similar Projects

China Diversion Reconstruction

China Diversion Reconstruction SERVICE STUDIO: Surveying Mapping & GIS, Material Testing & Inspection, Community Planning Location: Owyhee, Nevada Project Manager: Tom Hannum P.E./Brian Houston Brief This reconstruction project for the China Diversion out on the Owyhee River in Duck Valley,

Read More »

Great Basin Water Company-SCD Pipeline Replacement Project

Great Basin Water Company-SCD Pipeline Replacement Project SERVICE STUDIO: Community Planning, Civil Infrastructure Engineering, 1704 Special Inspection, and Material Testing & Inspection Location: Elko, Nevada Project Manager: Thomas Hannum, P.E./Nitin Bhakta, P.E. Brief Summit Engineering performed all the surveys needed

Read More »

Ruby Mountain Peaks Subdivision

Ruby Mountain Peaks Subdivision SERVICE STUDIO: Community Planning, Civil Infrastructure Engineering, Surveying Mapping & GIS, 1704 Special Inspection, Geotechnical Inspection, Material Testing & Inspection, Municipal, CIP, CM, & Inspection Location: Elko, Nevada Project Manager: Nitin Bhakta, P.E./Tom Hannum, P.E. A

Read More »

Woodland Village Phase 1-21

Woodland Village Phase 1-21 SERVICE STUDIO: Community Planning, Civil Infrastructure Engineering, Surveying, Mapping, & GIS, and Municipal, CIP, CM & Inspection Location: Cold Springs, Washoe County, Nevada Project Manager: Colin Hayes, P.E./Robert Gelu, P.E. Brief Summit Engineering was in responsible

Read More »

Pumpkin Hollow Mine

Pumpkin Hollow Mine SERVICE STUDIO: Mining Civil Support Services, Surveying, Mapping, & GIS, Geotechnical Inspection, and Material Testing & Inspection Location: Yerington, Nevada Project Manager: Joe Pursel, P.E./Ryan Cook PLS, WRS, CFedS Yerington Land Conveyance Summit’s Surveying Department was instrumental

Read More »

Black Mountain – Cell Tower

Black Mountain – Cell Tower SERVICE STUDIO: Construction Management & Inspection, Geotechnical Inspection, Material Testing & Inspection Location: Various Locations, Nevada Project Manager: Joe Pursel Brief Summit Engineering has had a longstanding partnership with S2M Tower and Network Services.  During

Read More »